Construction is underway for an alternative road to "Ala-Too Resort"
In the Ak-Suu district of Issyk-Kul region, work has intensified on the design and construction of an alternative road from Jyrgalan village to the "Ala-Too Resort" ski resort.
Currently, the mountain cluster, together with the Ministry of Transport and Communications of the Kyrgyz Republic, has begun laying a new road spanning **4.97 miles (8 km)**. This will serve as an alternative route from Jyrgalan village to the "Ala-Too Resort" ski resort. Work is now underway to widen previously used mountain trails, and a gravel-sand mixture is being laid on them. To date, crushed stone laying has been completed over **0.62 miles (1 km)** of the road. In parallel with the road widening, work is underway to relocate high-voltage power lines. More than 10 units of equipment and teams of specialists are involved.
In addition, construction has begun on the **8.7-mile (14 km)** road section from Toktogul village to Jyrgalan. Of this, work has been completed on **0.81 miles (1 km 300 m)** within the village limits, and road widening continues simultaneously. Preparatory work for the installation of the drainage line is also starting. In total, pipes will be laid on approximately 30 supports. Crushed stone is being delivered from the nearest quarry to the construction area. Approximately 30 units of equipment and about 30 workers are involved at the site. According to the plan, the crushed stone laying on the **8.7-mile (14 km)** road section will be completed by the end of the current year, and half of this road will be asphalted.
The project will also include the construction of a sidewalk and concrete drainage channels. As for the **5.28 miles (8.5 km)** of road, the crushed stone laying work should be completed by August 31st.
Back